Project:
Bailey Drive & South Brewer Street Walkway
City: Manchester
Contractor: Tschiggfrie Excavating Company
Field Completion: July 29, 2006
Construction Cost: $461,510.17
Project Description: The extent of the work involved consists of clearing and grubbing, excavation and grading of base, box culvert extension, drainage structures, base preparation, and paving of concrete walking trail with related subsidiary and incidental work.
Before Construction
|