TeKippe Engineering

Project: Water System Improvements

City: Greene

Contractor: Wunsch Construction, Inc.
Field Completion:  Summer 2008

Construction Cost: $452,000.00

Project Description:  The City of Greene had several areas in their community where fire hydrants did not meet State Standards.  In some parts, residents had very low water pressure in their homes.  To provide better flow to both residents and fire hydrants, a CAD model of the community was developed.  From this CAD model, TeKippe Engineering, P.C. was able to determine inadequate areas within the water system and model proposed improvements.  Project involved the installation of over 6900 feet of water main along with over 67 residential and commercial service connections.

During Construction



During Construction




During Construction