Project:
Dillon Street Sanitary Sewer Extension
City: Cascade
Contractor: F.L. Krapfl, Inc.
Field Completion: August 28, 2008
Construction Cost: $34,650.00
Project Description: The project consisted of the installation of an 8" diameter sewer main, manholes and related subsidiary work. When completed four properties previously served by private septic systems connected to the City sanitary sewer system.
During
Construction
During Construction
After Construction
|